| ====== Ticketing System ====== | ====== Ticketing System ====== | ||
| - | Following | + | Following document |
| * {{ : | * {{ : | ||
| + | It is feasible and based on your document i propose following implementation: | ||
| + | - adapting NIS touch panel interface for managing ticketing system (call on downtime, call without downtime, trace of time/state of maintenance evolution) | ||
| + | - adapting NIS Andon Board to show ticketing current state of the line | ||
| + | - implementing a simple GUI for announcing the creation of new ticket to maintenance worker, for assigning a ticket (*), for tracing a ticket (the best is as an APP for smart-device: | ||
| + | - implementing some reports extending the actual version of the same in NIS, and a page for managing ticket by managers users | ||
| + | - implementing standard interface for receiving / sending information to other Maintenance Software (for example using Rest-Service technology) | ||
| + | (*) in the future the system could use same algorithm of AIOCAP to select the best maintenance worker for specific problem... | ||
| + | In the document i saw that you talk about " | ||
| + | Regarding costs we could estimate the following: | ||
| + | - Costs for implementation of a prototype (one-shot: from 15k€ to maximum 20k€) | ||
| + | - Costs for integration with other maintenance system (one-shot-for-each-different-maintenance system to integrate: from 2k€ to 4k€) | ||
| + | - Costs for extending to other lines (one-shot-for-each-line: | ||
| + | - Costs for extending to other plants (one-shot-for-each-plant: | ||
| + | Regarding timing we could estimate the following: | ||
| + | * 2 months for prototype | ||
| + | * 2 weeks for testing the extention on some other lines in the same plant of the prototype | ||
| + | * 2 weeks for integration of other maintenance system (for each different maintenance system) | ||
| + | * 4 days for starting a new plant (more than one plant could be started at the same time) | ||
| + | * 1 day for starting 2 new lines | ||
| + | No hardware / cables estimated, this is a first budgetary evaluation, it's required to go deeper to refine it. | ||